Calculator
Enter your scope and assumptions. Defaults are conservative.
Example data table
These examples show how productivity and conditions change hours.
| Scenario | Area | Phase | Conditions | Productivity | Crew | Estimated hours | Estimated days |
|---|---|---|---|---|---|---|---|
| Small office final clean | 8,000 sq ft | Final | Medium debris, normal access | 420 / hr | 5 | 25.4 | 0.64 |
| Residential rough clean | 14,500 sq ft | Rough | Light debris, easy access | 520 / hr | 6 | 25.1 | 0.52 |
| Industrial turnover polish | 30,000 sq ft | Turnover | Heavy debris, tight access | 350 / hr | 10 | 152.6 | 1.91 |
| Multi-level retail final clean | 22,000 sq ft | Final | Medium debris, multi-level | 420 / hr | 8 | 73.9 | 1.15 |
| High access lobby detailing | 6,500 sq ft | Turnover | Light debris, high access | 410 / hr | 4 | 30.2 | 0.94 |
Use these as a reasonableness check, then calibrate with your historical data.
Formula used
The calculator estimates labor hours by combining an area-based baseline with condition multipliers and optional task line items.
- Base Hours = Area ÷ Productivity Rate
- Condition Factor = Phase × Building × Debris × Access × Height × (1 + Waste %)
- Adjusted Hours = Base Hours × Condition Factor
- Pre‑contingency Hours = Adjusted Hours + Extra Task Hours
- Total Hours = Pre‑contingency Hours × (1 + Contingency %)
- Duration (days) = Total Hours ÷ (Crew Size × Hours/Day)
- Labor Cost = Total Hours × Blended Hourly Rate
How to use this calculator
- Enter the project name and total area to be cleaned.
- Select the cleaning phase and building type for baseline complexity.
- Set productivity using site history, or click Use typical.
- Choose debris, access, and height settings that match field conditions.
- Add waste and contingency to reflect coordination and rework risk.
- Optionally add extra tasks for unit-based work items.
- Click Calculate to view results above the form.
- Use Download CSV or Download PDF for reporting.