Plan foundation budgets using customizable helical pier pricing. Compare scenarios with labor and materials rates. Get instant totals, plus per‑pier costs and summaries today.
| Scenario | Piers | Depth (ft) | Capacity (kips) | Material / Pier | Crew Rate | Equipment / Day | Contingency |
|---|---|---|---|---|---|---|---|
| Residential porch retrofit | 8 | 14 | 15 | $180 | $65/hr | $350 | 8% |
| Light commercial slab edge | 20 | 20 | 25 | $230 | $80/hr | $500 | 10% |
| Equipment pad with higher loads | 16 | 24 | 35 | $280 | $90/hr | $650 | 12% |
Project budgets are usually driven by pier quantity, unit material pricing, and installation productivity. This calculator separates direct costs (materials, labor, equipment, and fees) from markups, so you can see what moves the total. If you change only one variable at a time, you can isolate whether scope, means-and-methods, or commercial terms are driving the estimate.
Deeper embedment often requires longer shafts, extensions, and more handling time. Higher design capacity can imply larger helices or thicker steel, increasing material cost. The optional depth and capacity factors apply only to the base material rate, keeping labor and equipment adjustable. Use a realistic baseline (for example, 10 ft or 20 kips) that matches your typical jobs.
Crew hours per pier should reflect access, layout complexity, obstructions, and verification steps such as torque logging. For planning, many small projects fall between 1.5 and 3.0 crew-hours per pier, while constrained sites can be higher. Equipment rental days should include setup, repositioning, and demobilization, not only drilling time.
Mobilization covers travel, loading, and staging that do not scale with pier count. Engineering, permitting, and inspection fees can be fixed or semi‑fixed, so smaller jobs carry higher overhead per pier. Contingency is best tied to known risks (variable soils, schedule limits, utility conflicts). Overhead and profit are applied after contingency for transparent roll‑up.
Using 12 piers at 18 ft depth, a $220 base material rate, 1.8 hours per pier, and $75/hr labor, the estimate totals about $11,663.94 with 10% contingency, 12% overhead, and 10% profit (tax excluded). The cost per pier is about $971.99. Treat these as planning figures and adjust to local pricing and specifications.
| Example input / output | Value |
|---|---|
| Piers (qty) | 12 |
| Average depth (ft) | 18.00 |
| Base material cost per pier | $220.00 |
| Depth factor (baseline 10 ft, 1.5%/ft) | Enabled |
| Adjusted unit material cost | $246.40 |
| Labor (1.8 hr/pier @ $75/hr) | $1,620.00 |
| Equipment (2 days @ $450/day) | $900.00 |
| Mobilization + fees | $2,050.00 |
| Total project cost (tax excluded) | $11,663.94 |
| Cost per pier | $971.99 |
It divides the full project total by pier quantity, including materials, labor, equipment, fees, and markups. It helps compare scenarios, but it is not a stand‑alone unit price for purchasing piers.
This calculator applies contingency first, then overhead, then profit. Many estimators prefer this order because it reflects how uncertainty affects the managed cost base and keeps the roll‑up transparent.
Start with past job logs, then adjust for access, obstructions, weather allowances, and verification requirements. If you lack history, run low/most‑likely/high scenarios (for example, 1.5, 2.0, and 3.0 hours).
Enable it when material cost grows with deeper embedment beyond a typical baseline. Set the baseline to your “standard” depth, then use a conservative percent per foot that matches your supplier pricing or historical purchase orders.
Not directly. Add geotechnical reports, test borings, and specialty engineering as part of the engineering/design fee or as an added allowance, depending on how you track preconstruction and project soft costs.
Mobilization is often a fixed cost: travel, loading, staging, and setup happen even with a few piers. On small scopes, these fixed costs can dominate the per‑pier figure, so they should be explicit.
Yes. Download CSV for spreadsheets and audit trails, and download PDF for sharing a clean breakdown. For client proposals, add notes about exclusions, assumptions, and whether taxes and permits are included.