Turn progress updates into reliable time forecasts. Include productivity shifts, delays, and recovery actions easily. Get remaining duration, finish dates, and buffer guidance fast.
| Scenario | Total duration | Elapsed | % complete | Productivity | Delay | Rework | Residual (approx.) |
|---|---|---|---|---|---|---|---|
| Baseline | 90 days | 30 days | 35% | 1.00 | 5 days | 3% | ~64.6 days |
| Faster crews | 90 days | 30 days | 35% | 1.15 | 3 days | 2% | ~55.0 days |
| More disruption | 90 days | 30 days | 35% | 0.90 | 10 days | 5% | ~81.4 days |
This calculator estimates the remaining schedule time after considering progress, productivity, expected delays, rework allowance, and optional recovery actions.
Residual duration translates field progress into remaining time, helping planners confirm whether the baseline finish is still realistic. When the residual grows faster than elapsed time, it signals scope creep, productivity loss, or underestimated constraints. Use the output to prioritize corrective actions before float is exhausted.
Percent complete works best when tied to measurable quantities: installed meters, poured cubic volume, tested circuits, or closed work packages. Avoid subjective “looks done” updates. A consistent measurement method reduces volatility in residual results and improves forecast credibility for stakeholders.
The productivity factor scales remaining effort versus baseline. For example, a factor of 1.15 indicates production is 15% faster, reducing adjusted remaining time. Track causes such as learning curves, overtime fatigue, material handling, or access limitations. Update the factor weekly to reflect actual production rates.
Delay allowance captures expected interruptions like inspections, weather windows, or permit holds. Rework percent covers punch list, design clarifications, and quality defects that consume time without adding new scope. If recovery actions are planned—additional crews, resequencing, or extended shifts—use acceleration to model realistic time reduction.
A buffer percent provides a conservative residual for risk management. Apply higher buffers when uncertainty is high or dependencies are unresolved. Report both residual and residual-with-buffer alongside key assumptions, so leadership can decide whether to invest in recovery, adjust milestones, or renegotiate handoffs.
It is the estimated remaining time to complete the current scope, adjusted for progress, productivity, delay allowance, rework, and any planned acceleration actions.
Quantity-based progress is usually more reliable. Tie percent complete to installed quantities or closed packages, and keep the method consistent across reporting periods.
Compare actual production rates to baseline assumptions. If crews produce 10% more per day than planned, use 1.10. If 15% less, use 0.85.
Include expected interruptions that add time without adding scope, such as inspections, weather exposure, access restrictions, client holds, and permit dependencies.
Rework commonly scales with unfinished work and upcoming interfaces. Using base remaining keeps the allowance proportional to what is left to build and verify.
Use buffer when uncertainty is high: incomplete design, many handoffs, long-lead items, or volatile site conditions. Report buffered and unbuffered residual to support decisions.
No. It is a fast forecasting aid. Use it alongside a detailed schedule, logic checks, and resource analysis for contract milestones and critical path decisions.
Use professional judgment for critical schedule decisions.
Use professional judgment for critical schedule decisions.Important Note: All the Calculators listed in this site are for educational purpose only and we do not guarentee the accuracy of results. Please do consult with other sources as well.