SPI CPI Calculator

Measure project performance fast using earned value indicators. Spot schedule slips and cost overruns early. Export reports, share progress, and align teams every week.

Calculator Inputs

Budgeted cost of scheduled work.
Budgeted cost of completed work.
Actual cost of completed work.
Total planned budget for the project.
Used only when BAC is provided.
Days or weeks—keep units consistent.
Enables a simple planned/actual time ratio.
Reset

Example Data Table

Use these sample values to see how the metrics behave.

Scenario PV EV AC SPI CPI
On schedule, under budget 100000 100000 95000 1.0000 1.0526
Behind schedule, over budget 120000 100000 110000 0.8333 0.9091
Ahead of schedule, over budget 90000 105000 115000 1.1667 0.9130

Formulas Used

  • SPI = EV / PV
  • CPI = EV / AC
  • SV = EV − PV
  • CV = EV − AC
  • Percent Complete = (EV / BAC) × 100
  • EAC (method choices):
    • EAC = BAC / CPI
    • EAC = AC + (BAC − EV)
    • EAC = AC + (BAC − EV) / (CPI × SPI)
  • ETC = EAC − AC
  • VAC = BAC − EAC

How to Use This Calculator

  1. Enter PV, EV, and AC for the same reporting date.
  2. Optionally add BAC to estimate EAC, ETC, and VAC.
  3. Choose an EAC method that fits your control approach.
  4. Press Submit to view results above the form.
  5. Download CSV or PDF to share with your team.

FAQs

1) What does SPI indicate?

SPI compares earned value to planned value. Values above 1 mean progress is ahead of plan; below 1 means behind plan for the same point in time.

2) What does CPI indicate?

CPI compares earned value to actual cost. Values above 1 suggest cost efficiency; below 1 indicates you spent more than planned for completed work.

3) Can SPI and CPI be used together?

Yes. Together they show whether the project is progressing fast enough and spending efficiently. A project can be ahead of schedule but over budget, or vice versa.

4) When should I provide BAC?

Provide BAC when you want forecasting outputs such as EAC, ETC, and VAC. Without BAC, you still get SPI, CPI, and variances for performance diagnosis.

5) Which EAC method should I choose?

Use BAC/CPI when future work follows current cost efficiency. Use AC+(BAC−EV) when remaining work matches the original plan. Use the CPI×SPI option when both cost and schedule trends persist.

6) Why must PV, EV, and AC use the same date?

Earned value metrics are meaningful only when all values refer to the same reporting cutoff. Mixing dates can distort indices and lead to incorrect corrective actions.

7) What if EV is zero?

If EV is zero, the indices may be zero, signaling no measurable progress. Confirm that work is truly incomplete and that progress measurement rules are consistent across the team.

Note: This calculator provides decision support, not a replacement for project governance.

Related Calculators

project npv calculatoron time delivery calculatorproject irr calculatorproject variance calculator

Important Note: All the Calculators listed in this site are for educational purpose only and we do not guarentee the accuracy of results. Please do consult with other sources as well.