Measure project performance fast using earned value indicators. Spot schedule slips and cost overruns early. Export reports, share progress, and align teams every week.
Use these sample values to see how the metrics behave.
| Scenario | PV | EV | AC | SPI | CPI |
|---|---|---|---|---|---|
| On schedule, under budget | 100000 | 100000 | 95000 | 1.0000 | 1.0526 |
| Behind schedule, over budget | 120000 | 100000 | 110000 | 0.8333 | 0.9091 |
| Ahead of schedule, over budget | 90000 | 105000 | 115000 | 1.1667 | 0.9130 |
SPI compares earned value to planned value. Values above 1 mean progress is ahead of plan; below 1 means behind plan for the same point in time.
CPI compares earned value to actual cost. Values above 1 suggest cost efficiency; below 1 indicates you spent more than planned for completed work.
Yes. Together they show whether the project is progressing fast enough and spending efficiently. A project can be ahead of schedule but over budget, or vice versa.
Provide BAC when you want forecasting outputs such as EAC, ETC, and VAC. Without BAC, you still get SPI, CPI, and variances for performance diagnosis.
Use BAC/CPI when future work follows current cost efficiency. Use AC+(BAC−EV) when remaining work matches the original plan. Use the CPI×SPI option when both cost and schedule trends persist.
Earned value metrics are meaningful only when all values refer to the same reporting cutoff. Mixing dates can distort indices and lead to incorrect corrective actions.
If EV is zero, the indices may be zero, signaling no measurable progress. Confirm that work is truly incomplete and that progress measurement rules are consistent across the team.
Important Note: All the Calculators listed in this site are for educational purpose only and we do not guarentee the accuracy of results. Please do consult with other sources as well.