Estimate installation hours and crew days fast for jobs. Compare scenarios, add prep tasks, and export summaries for confident planning.
| Scenario | Area | Crew | Rate | Complexity | Labor Days | Calendar Days |
|---|---|---|---|---|---|---|
| Rental refresh | 900 ft² | 2 | 55 ft²/hr | 1.00 | 2.00 | 2.00 |
| Occupied home | 750 ft² | 2 | 45 ft²/hr | 1.25 | 2.75 | 2.75 |
| Tile with cure | 600 ft² | 3 | 22 ft²/hr | 1.40 | 3.25 | 4.25 |
A realistic schedule protects downstream trades and reduces change orders. For residential projects, a one-day slip can cascade into delayed paint, trim, and appliance installs. This calculator converts scope into labor days and calendar days so you can coordinate crews, access windows, and material deliveries.
Start with measured floor area, then add waste for cuts and pattern alignment. Straight plank layouts often use 5–10% waste, while diagonal patterns and small rooms can push 12–18%. The calculator uses Net Area to keep the production math consistent.
Productivity varies by material and site constraints. Many crews report higher rates on click plank systems than on tile where layout, mixing, and cleanup slow progress. If you are unsure, run three scenarios: conservative, expected, and best-case to see how the labor days move.
Adding installers can shorten duration, but congestion and shared tools reduce gains in tight spaces. Two installers in 750 ft² often outperform four installers if rooms are narrow. Use the crew input with a modest efficiency value to reflect coordination time and walk paths.
Complexity increases when you have many doorways, closets, islands, or detailed borders. A factor of 1.00 fits open rectangles, 1.25 fits typical furnished homes, and 1.40–1.60 fits heavy scribing, tile patterns, or multiple transitions. Adjust it instead of inflating the base rate.
Time is frequently lost before the first plank is laid. Removal, floor leveling, moisture barriers, and underlayment can take several hours per room. Transition strips, baseboards, and thresholds also add measurable time; capturing these as separate hours improves forecast accuracy.
Efficiency accounts for interruptions: material staging, tool changes, dust control, and client access. Many schedules assume 80–90% efficiency for occupied homes and 90–95% for vacant units. Breaks and downtime reduce productive hours/day, which the calculator subtracts directly.
Some systems add non-labor waiting time. Adhesives, grout, and coatings may require 12–48 hours before foot traffic or heavy loads. Enter cure hours to convert waiting into calendar days, then align inspections and punch lists so the space is ready for turnover.
Use a rate your crew has achieved on similar jobs. If unknown, test three rates: low, expected, and high. Keep the complexity factor near 1.0 when rate already includes typical cutting and room changes.
Yes, if your schedule covers the full floor scope. Enter removal hours so the labor days reflect reality. If demolition is a separate crew or day, set demolition hours to zero and plan it separately.
Run separate calculations for each material area because rates differ. Then add the labor days together and account for extra transition and cleanup hours. This approach is clearer than blending rates into one average.
Crowding, shared cutting stations, and limited staging space create waiting time. In small rooms, two installers can work continuously while additional installers compete for space. Lower the efficiency percent to reflect these constraints.
No. Cure time adds calendar days, not crew-hours. The calculator keeps labor and waiting separate so you can schedule return visits, inspections, and move-in timing without overstating installer labor.
Many straight plank layouts use 5–10% waste. Diagonal installs, patterned tile, or irregular rooms can require 12–18% or more. When in doubt, model two waste values and compare net area impact.
Break the job into tasks you can defend: prep, layout, install, trim, and inspection. Use measured room counts and realistic daily working hours. After completion, compare actuals and update your base rate for future jobs.