Inputs
Use realistic productivity and rates for your site conditions.
Tip: If efficiency is 80%, hours rise by 25%.
Formula Used
The calculator uses crew-hours for production, then converts to person-hours by role.
- Crew hours (raw) = Quantity ÷ Productivity
- Crew hours (adjusted) = Crew hours (raw) ÷ Efficiency
- Duration (days) = Crew hours (adjusted) ÷ (Shifts × Hours/shift)
- Travel hours = (Travel minutes/60) × Duration(with delays) × Crew size
- Role hours = Direct hours + allocated shared hours, then × (1 + Contingency)
- Role cost = Regular hours × Rate + Overtime hours × (Rate × Multiplier)
- Total cost = (Sum role costs × (1 + Burden)) × (1 + Overhead+Profit)
How to Use This Calculator
- Enter your total scope quantity and unit label.
- Set productivity as units completed per crew-hour.
- Define crew makeup and realistic hourly rates.
- Adjust efficiency for site constraints and learning.
- Add travel, mobilization, setup, and supervision factors.
- Include overtime, burden, and overhead/profit if needed.
- Press Calculate, then export CSV or PDF reports.
Example Data Table
| Item | Example Value | Notes |
|---|---|---|
| Quantity | 120 | Scope for a small zone |
| Unit Label | m² | Surface-based installation |
| Productivity | 6 | Units per crew-hour |
| Crew (I/H) | 2 / 1 | Two installers and one helper |
| Efficiency | 85% | Access limitations and coordination |
| Delay Allowance | 5% | Inspections and workface readiness |
| Contingency | 10% | Rework and productivity variance |
| Overtime Share | 10% | Short schedule push |
| Burden | 18% | Fringe and statutory costs |
| Overhead+Profit | 12% | Markup for project recovery |
Enter these values above and click Calculate to see a full breakdown.