Installation Labor Calculator

Clear labor forecasts for every construction install. Include helpers, supervision, mobilization, and delay allowances today. Turn inputs into accurate labor budgets in minutes now.

Inputs

Use realistic productivity and rates for your site conditions.
Tip: If efficiency is 80%, hours rise by 25%.
Total install scope in chosen units.
Examples: m², m, pcs, panels.
Crew-hour means one hour with the full crew.
Skilled workers performing installation.
Material handling, staging, support tasks.
Accounts for congestion, access, learning curve.
Use 2 or 3 for accelerated schedules.
Defines available work time each day.
Gate access, walking distance, tool movement.
Permits, staging, initial setup, unloading.
Tooling, safety checks, cleanup allowance.
Weather, inspections, coordination, hold points.
Covers rework risk and productivity variance.
Supervisor hours per crew-hour (e.g., 15%).
Percent of hours billed at overtime rate.
Common values: 1.25, 1.5, 2.0.
Fringe, insurance, taxes, benefits.
Applied after burdened labor cost.
Used for display and exports.

Hourly Rates

Base wage before burden and overtime.
Use blended rate if multiple helper grades.
Applied using supervision factor above.
Reset

Notes: Productivity is per crew-hour. If your productivity is per worker-hour, multiply it by crew size.

Formula Used

The calculator uses crew-hours for production, then converts to person-hours by role.
  • Crew hours (raw) = Quantity ÷ Productivity
  • Crew hours (adjusted) = Crew hours (raw) ÷ Efficiency
  • Duration (days) = Crew hours (adjusted) ÷ (Shifts × Hours/shift)
  • Travel hours = (Travel minutes/60) × Duration(with delays) × Crew size
  • Role hours = Direct hours + allocated shared hours, then × (1 + Contingency)
  • Role cost = Regular hours × Rate + Overtime hours × (Rate × Multiplier)
  • Total cost = (Sum role costs × (1 + Burden)) × (1 + Overhead+Profit)

How to Use This Calculator

  1. Enter your total scope quantity and unit label.
  2. Set productivity as units completed per crew-hour.
  3. Define crew makeup and realistic hourly rates.
  4. Adjust efficiency for site constraints and learning.
  5. Add travel, mobilization, setup, and supervision factors.
  6. Include overtime, burden, and overhead/profit if needed.
  7. Press Calculate, then export CSV or PDF reports.

Example Data Table

Item Example Value Notes
Quantity120Scope for a small zone
Unit LabelSurface-based installation
Productivity6Units per crew-hour
Crew (I/H)2 / 1Two installers and one helper
Efficiency85%Access limitations and coordination
Delay Allowance5%Inspections and workface readiness
Contingency10%Rework and productivity variance
Overtime Share10%Short schedule push
Burden18%Fringe and statutory costs
Overhead+Profit12%Markup for project recovery

Enter these values above and click Calculate to see a full breakdown.

Related Calculators

Paver Sand Bedding Calculator (depth-based)Paver Edge Restraint Length & Cost CalculatorPaver Sealer Quantity & Cost CalculatorExcavation Hauling Loads Calculator (truck loads)Soil Disposal Fee CalculatorSite Leveling Cost CalculatorCompaction Passes Time & Cost CalculatorPlate Compactor Rental Cost CalculatorGravel Volume Calculator (yards/tons)Gravel Weight Calculator (by material type)