Plan smarter maintenance budgets using forecasts tailored to equipment life today easily. Compare scenarios, see present-value impacts, and export tables for meetings fast anywhere.
| Parameter | Example value | Notes |
|---|---|---|
| Study period | 10 years | Common for fleet budgeting |
| Discount / Inflation | 8% / 3% | Used for present value and nominal growth |
| Routine year‑1 total | 13,000 | Preventive + corrective + inspection |
| Maintenance escalation | 1.5% | Extra wear-and-tear increase |
| Major events | Year 3: 12,000; Year 6: 8,000 | Overhaul and major repair |
| Salvage | 25,000 | Subtracted in the final year |
| Output | PV total + yearly table | Use PV for option comparisons |
Routine cost growth (nominal):
RoutineNom(y) = RoutineBase × (1 + g)y−1, where g = (1+inflation)×(1+escalation) − 1
One-time event inflation (nominal):
EventNom(y) = EventBase × (1 + inflation)y−1
Contingency:
AdjustedNom(y) = Nominal(y) × (1 + contingency)
Present value:
PV(y) = AdjustedNom(y) ÷ (1 + r)y
For real discounting, r is derived as: r = (1+discount)/(1+inflation) − 1.
Equivalent annual cost (EAC):
EAC = NPV × [ r(1+r)N ] ÷ [ (1+r)N − 1 ]
Construction assets rarely fail all at once; costs drift upward as parts wear, utilization changes, and service intervals tighten. A structured life-cycle forecast turns scattered work orders into a predictable cashflow plan that supports bids, capital requests, and long-term reliability targets. A 10-year view reveals budget cliffs early.
Start with a defensible year‑1 baseline: preventive tasks, corrective repairs, inspections, and routine consumables. If you track costs by asset class, use averages for similar machines and remove outliers from one-off breakdowns. The calculator treats this baseline as the anchor for future growth. Include labor and parts.
Inflation lifts nearly everything, but aging introduces an additional slope. Many fleets see routine maintenance rise by a few percent annually beyond inflation once equipment passes mid‑life. By modeling inflation and maintenance escalation separately, you can test whether reliability programs flatten the escalation curve. Document assumptions for auditability.
Big-ticket interventions should be scheduled explicitly: engine rebuilds, structural refurbishments, resurfacing, repainting, or sensor upgrades. Assign each event to a year and cost in base-year money; the forecast inflates it into that year, then discounts it to present value for comparisons. Overhauls often equal about one year of routine spend.
Replacement is a timing choice: pay a large amount in a specific year to reset condition, then recover value at the end through salvage. When replacement costs outweigh rising maintenance, the present value total will signal whether earlier replacement reduces the equivalent annual cost over the study period. Compare replacement years for break-even.
Present value converts future spending into today’s terms using a discount rate. For stakeholders, EAC is often easier to interpret: it spreads the life‑cycle present value into a constant annual budget figure. This helps align maintenance planning with annual operating budgets. Higher discount rates reduce far-future PV impact.
Uncertainty is normal: parts lead times, labor availability, and site conditions shift costs. A contingency factor applies a consistent uplift to each year’s total so you can communicate a risk‑aware plan. Keep contingency transparent and revise it as cost data quality improves. Pair contingency with PM compliance and spares planning.
Small rate changes can materially affect multi‑year forecasts. Run alternative escalation values to see the present value swing, then focus improvement efforts where sensitivity is highest. Over time, calibrate rates using actuals, update event timing, and re-export the tables for reviews and audits. A simple ±1% test guides priorities.
Inflation raises general prices over time. Maintenance escalation represents extra growth from aging, heavier use, or deteriorating conditions. Modeling both separately helps you avoid double counting while still reflecting real wear-and-tear.
Use nominal discounting when your discount rate already includes inflation and your cashflows are inflated. Use real discounting when you prefer inflation-adjusted rates. The tool supports both and derives the real rate automatically.
Use vendor quotes, historical overhaul invoices, or standardized job plans. Enter costs in base-year money, then assign the year they occur. Keep event definitions consistent so future updates compare cleanly.
Contingency covers uncertainty in labor hours, parts pricing, access constraints, and unplanned findings. It creates a risk-aware budget and can be reduced as data quality and maintenance controls improve.
Salvage is treated as a negative cost in the final year of the study period. It is inflated to that year and then discounted like other cashflows, reducing the overall present value total.
Yes. Adjust escalation, event timing, or replacement year and recalculate. Use the PV total and EAC to compare options on a consistent basis. Export the yearly table to document decisions.
Enter operating hours per year as an average across seasons. If seasonal usage changes costs materially, run separate scenarios with different hours and escalation assumptions, then compare PV cost per operating hour.
Use results to plan, fund, and maintain assets confidently.