Inputs
Advanced options includedResults
| Metric | Value |
|---|
Example data table
Typical cases for quick reference. Change inputs above and recalc for your project.
| Diameter (in) | Height (in) | Count | Waste % | Volume (ft³) | Volume (yd³) | 80 lb bags |
|---|
Formula used
Cylinder volume: V = π · D² / 4 · H. Use consistent units for diameter D and height H.
- Imperial: inches → feet:
Dft = Din/12,Hft = Hin/12, soVft³ = π·(Dft²)/4·Hft. - Metric: millimeters → meters:
Dm = Dmm/1000,Hm = Hmm/1000, soVm³ = π·(Dm²)/4·Hm. - Apply waste:
Vtotal = V · count · (1 + waste%). - Bag counts: divide total volume by per‑bag yield and round up.
- Concrete weight:
W = ρ · Vwhere ρ is density in matched units. - Rebar weight: verticals + hoops. Verticals length ≈
H − 2·cover. Hoops count ≈⌊(H−2·cover)/spacing⌋ + 1. Hoop length ≈ circumference at clear diameter.
Per‑bag yields used here: 40 lb → 0.30 ft³, 50 lb → 0.375 ft³, 60 lb → 0.45 ft³, 80 lb → 0.60 ft³; 20 kg → 0.009 m³, 25 kg → 0.012 m³, 30 kg → 0.014 m³. Verify with your supplier.
How to use
- Choose units and enter tube diameter and height/depth.
- Set number of tubes and optional waste percentage.
- Adjust concrete density if required by spec or mix design.
- (Optional) Toggle rebar; set bar size, count, cover, and hoop spacing.
- Click Calculate to see volumes, weights, and bag counts.
- Export your results as CSV or PDF for submittals or procurement.