| Item | Value |
|---|
Click a row to load its inputs.
| # | Units | Mode | Area / L×W | Width | Length | Side lap % | End lap % | Waste % |
|---|---|---|---|---|---|---|---|---|
| 1 | Metric | Area | 150 m² | 1.0 m | 10 m | 10 | 15 | 5 |
| 2 | Metric | Layout | 20 m × 8 m | 1.2 m | 15 m | 8 | 12 | 7 |
| 3 | Imperial | Area | 2000 ft² | 3 ft | 65 ft | 10 | 12 | 5 |
Effective coverage per roll
weff = w × (1 − sideLap/100)leff = l × (1 − endLap/100)Aroll = weff × leffAnet = Aroll × (1 − waste/100)
By Total Area mode
Narea = ceil( Aproject / Anet )
By Rectangular Layout mode
- Number of courses:
ncourses = ceil( D⊥ / weff ), whereD⊥is the dimension perpendicular to run orientation. - Rolls per course:
nper-course = ceil( Drun / leff ) - Raw rolls:
Ncourse-raw = ncourses × nper-course - With waste:
Ncourse = ceil( Ncourse-raw × (1 + waste/100) )
Final selection
N = max( Narea, Ncourse )
- Choose your unit system and calculation mode.
- Enter roll width, length, and lap percentages from the datasheet.
- In Area mode, type the total area. In Layout mode, enter project length and width and choose orientation.
- Set an appropriate waste percentage for detailing and offcuts.
- Press Calculate. Export the summary as CSV or PDF, or copy a shareable link.
Tip: Increase end laps for slopes or critical waterproofing zones.
- This tool provides estimates only and does not replace project-specific detailing.
- Verify substrate prep, primers, and accessory quantities separately.
- Always comply with the membrane system supplier’s published guidance.